Status of VMS backups of tmp and prj$root disks
Applications not ported to UNIX
Stages of VMS retirement
VMS Retention Requests
What to do next Tuesday
The TNG backups are in the first stage of making backup tapes.
The assumption that there "exist other copies of important data (as
that was the data area manager's responsibility) and that these are emergency
backups, only" was restated and reaffirmed by the group.
| FNALD0 | TNG | D0FS | D0SFT | D0IT |
| Trigsim | DECnet Phase V router | |||
| Pixcie | Pixie | |||
| Pickevents Client | Pickevents Client | Pickevents Server | ||
| Luminosity | Luminosity | |||
| RDB | RDB | |||
| Fatman Client | Fatman Client | Fatman Server |
Although there were concerns expressed, it was general agreement that
"no applications were only available on the
TNG cluster". There were applications that "could only be run
a VAX" so if only one of the two workstation clusters
remained it had to be FNALD0.
Alan is the only known user of D0SFT and tasked with migrating the distribution
functions off the machine. The
retirement date for D0SFT was September 1, 1999.
Removing the data areas of desktop machines so that workstations no longer had to serve disksRetirement dates for data areas have been posted (and are reprised below) and area managers should move or backup important information. Backups will be made to protect forgotten or orphaned data.
Replace the screens so that users no longer needed the desktop VMS machines
On December 1, 1999 all VMS (desktop ?) machines at D0 will be retired, regardless of clusters. The cluster cores, located in Feynman, will continue to provide the identified residual functions required. By December 1, all purchases necessary to replace the VMS workstations need to be complete and the support arrangements made. The approved D0 Run II desktop is a PC and guidance can be found <where?>.
The following is the current environment for each cluster.
|
TNG
|
FNALD0
|
D0IT
|
|
| Total nodes |
25
|
37 |
12
|
| Boot nodes |
1
|
5
|
2
|
| Server nodes |
2
|
2
|
0
|
| Fermi owned workstations |
2
|
5
|
6
|
| University owned workstation |
20
|
19
|
4
|
| Down or dead machines |
4
|
20
|
On Tuesday, July 20, the DOIT cluster will be retired. Screens that have been identified as needing to continue will be served either by FNALD0 nodes or by replacement with PCs. This may take a little longer to implement.
It was decided that for FNALD0 the core functions could be consolidated
into D0GS01, D0GS06 and D0GSLB.
There was some discussion that the core functionality was really just
D0GS01 and D0GSLB. A determination
of the remaining disks would have to be made but it was desired to
keep the 6 home area disks, the two
scratch disks (for emergencies), the d0 and LB library disks
and the Fermi d0 products disks.
A number of possible designs were discussed. One was to combine
the "remains" of the FNALD0, TNG and DOFS
clusters into one remaining cluster. This would involve replacing
the Client Server relationship of D0FS to the other
two clusters and nobody was sure how to do it (or even if it was possible
to do).
The alternative was to consolidate D0FS, TNG and FNALD0 into as small
as possible clusters and "living with the results"
There was general agreement that this solution was feasible and a likely
requirement for any alternative solution.
Analyses using FNALD0 resources need to be submitted for publicationAnalyses submitted for publication before the deadline may keep necessary resources until they have been published.
by August 1st, or they should be ported to Unix systems.Analyses using TNG resources need to be submitted for publication
by Sept. 1st, or they should be ported to Unix systems.
There was a request by Nick Hadley that "somebody" (Darien Wood or designee)
needed to build a list of "successful users that have already converted
to UNIX".
>tmp$root358 Di-Lepton mSUGRA Until
PRL accepted Genik
>tmp$root320 analysis
or D0TNG shutdown
>tmp$root353
These were approved until Sept 1st or the user would have to convert
>tmp$root336
This was approved until Sept 1st or the user would have to convert
>prj$root317 W+jets color
Until publication Varelos
>tmp$root320 coherence
These were approved until Sept 1st or the user would have to convert
>Raja1 Energy
calibration Forever
Raja
>Raja3
code
>Raja4
This was NOT approved. The backups were determined to be sufficient
>tmp$root346 QCDWZ ntuple maker Until
port done Gerber
This was approved until Sept. 1st
>prj$root313 Wpt, Zpt, alpha-2 May
2000 Gerber
The Wpt project needs to convert to UNIX now
The Zpt was approved until Sept 1st (or needs to be converted)
The alpha-2 was unlikely to make the Sept 1st deadline so it should
be converted, now.
>tmp$root316 some analysis
for thr summer Casey
This was approved until Sept 1st or the user would have to convert
>prj$root352 trigger studies
1 month
Hirosky
>prj$root345 QCD Jets PRD
Month or so Hirosky
These were approved until Sept 1st or the user would have to convert
>tmp$root329 Pomeron exchange
September? Hirosky
The Pomeron exchange needs to be converted since it would probably
not
make the Sept 1st. deadline.
>prj$root310 QCD
> summer Babukhadia
>prj$root327 QCD
>prj$root310 QCD analysis
indefinite Nang
>prj$root327 QCD analysis
indefinite Nang
These were approved until Sept 1st or the user would have to convert
>prj$root325 upg simulator
indefinite Nang
This needs to be converted now.
>dair01$dka600 WZ cross section until
publication Gomez
This was approved until Sept 1st or the user would have to convert
>prj$root307 "files accessed"
indefinite Gerber
Not approved unless more information was provided
>tmp$root332 "finish a few jobs" indefinite
Landsberg
Approved until Aug 1st or a better explanation was provided
>NEW_PHENOM_4 SUSY R-parity
1 week
Qian
This was approved until Sept 1st or the user would have to convert
>d0fm12 DOIT node
until replaced Fuess For
Chinese collab.
>d0fm22 DOIT
node until
replaced Fuess For Chinese
collab.
These were approved until Stu Fuess can replace them
>d0ru01 DOIT node
indefinite Adams
This was approved until Mike Diesburg can replace it
>d0fm26 DOIT
until PC arrives Cummings
This was approved until PC arrives
>d0isu2 fnald0
indefinite Mauritz
Approved until Mike Diesburg can replace it
>d0az07 DOIT
until PC arrives Johns
Approved until PC arrives
>d0cd03 xfer Tau
stuff,mail 2 weeks
Qz. Li
Approved until Aug 1st
>d0br03 DOIT node
"For the time being"
>d0hs03 EWS Station!!
indefinite Gomez
>d0fm11 Support
d0hs03 indefinite
Gomez
>d0ku01 fnald0
?
Baringer
It was decided that Mike Diesburg and Dane Skow would replace these
>daumi1 TNG
indefinite Turcot
>dana01 TNG
indefinite Martin
TNG workstations are not scheduled for decommissioning until Sept
1st